The WRD had claimed that a supervision mechanism was in place but the CAG report said that no record was made available on any communications between the Section Officer (in-charge of the tank) with departmental/government officials.
Even if there was communication with the Chief Engineer as claimed by the WRD, the fact remains that the actual inflow and outflow was not regulated as per Central Water Commission (CWC) norms, the report charged.
The WRD had the opportunity to store 0.268 thousand million cubic feet (tmc) more at the tank where the storage stood at 3.377 tmc on December 1, 2015 at 2 pm when the discharge was increased from 12,000 cusecs to 20,960 cusecs.